Brent Cross West

Project Scope: Development of mainline station

Project Industry: Commercial

London’s newest high profile transport project.

Brent Cross West, the first mainline station to open in London in over ten years, cost over £419 million pounds to complete.

The station was originally scheduled to open in 2030 following approval in May 2020. However, the opening was brought forward to accommodate Brent Cross town. A vibrant and sustainable new town built from scratch that includes various amenities such as shops, bars, restaurants, and office spaces. 

We supplied our Farmhouse Orange Linear handmade bricks, the station also features exposed brickwork throughout the interiors, which were specifically chosen for their ability to give the station an established appearance.

 

 

 

 